
Greetings!
A number of years ago as a part of the City of Lima’s strategic planning process, the beautification of the Bellefontaine & Market Street entrance to the city was identified and prioritized. This targeted effort focused on blight removal, installation of safety enhancements such as lighting and traffic signs and signals, and aesthetic improvements such as trees and signage. Thus, over the years, we have seen the transformation of the City’s most blighted neighborhood made possible by investments by many public and private entities. The Bellefontaine & Market Street corridor is now home to the Lima Senior High School Campus, Spartan Stadium, and the new Lima Stadium Park. Soon we will see the opening of Dominion Energy’s new corporate campus.
Throughout this period we have also been working to address the major bottleneck and safety constraint presented by the Indiana & Ohio Railroad crossing. Rail activities at this crossing tie up vehicular traffic multiple times each day for unpredictable, and often lengthy, periods of time. Many anecdotes have arisen regarding doctors, nurses and other safety personnel being unable able to access our hospitals as a result. The most high profile incident involved a train that nearly stopped President Oba ma’s motorcade out of the city following his visit here in 2012.
Beginning with the receipt of two federal earmarks totaling $2.4 million secured by U.S. Congressman Michael Oxley in 2005, the city has now put in place a total of $13.8 million to construct an underpass on East Elm Street. Also included in the project will be a traffic circle to be constructed at the Elm, Bellefontaine and Calumet intersection to facilitate thru traffic and Spartan Stadium traffic during events. This project is scheduled to begin in the Spring of 2018 and be fully implemented by November 2019.
Many people and organizations are to be thanked for their help in making this project a reality, including the late Congressman Michael Oxley, ODOT Director Jerry Wray, ODOT District One Deputy Director Kirk Slusher, Lima Memorial Hospital, St. Rita’s Medical Center, Lima Allen County Regional Planning Commission, G&W Railroad, City of Lima Department of Public Works, City of Lima Department of Community Development, Lima City Council, American Structurepoint, DLZ, and the citizens of Lima.
We hope that you will use this website to stay up-to-date about route changes, road closures, and other project related events.
This Week:
1. Place topsoil to backup new sidewalk along Elm Street.
2. Winter seed of slopes adjacent to new bridge to prevent erosion of the areas.
Next Week:
1. Close Bellefontaine Avenue to through traffic on December 2nd and begin construction of the roundabout.
2. Open Elm Street to through traffic utilizing the temporary pavement along Bellefontaine Avenue.
3. Begin installation of new 24” sanitary sewer along Bellefontaine Avenue.

This Week:
1. Place topsoil to backup new sidewalk along Elm Street.
2. Winter seed of slopes adjacent to new bridge to prevent erosion of the areas.
Next Week:
1. Close Bellefontaine Avenue to through traffic on December 2nd and begin construction of the roundabout.
2. Open Elm Street to through traffic utilizing the temporary pavement along Bellefontaine Avenue.
3. Begin installation of new 24” sanitary sewer along Bellefontaine Avenue.

This Week:
1. Placing 304 aggregate base and curb on Elm St. from Grove Ave. to Shawnee St.
2. Backfilling behind rear and forward wingwalls on new bridge structure.
Next Week:
1. Placing 301 Asphalt Concrete Base and 448 Type 2 on Elm St. from Grove Ave. to Shawnee St.
2. Placing sidewalks along Elm St.

This Week:
1. Placing 304 aggregate base and curb on Elm St. from Grove Ave. to Shawnee St.
2. Backfilling behind rear and forward wingwalls on new bridge structure.
Next Week:
1. Placing 301 Asphalt Concrete Base and 448 Type 2 on Elm St. from Grove Ave. to Shawnee St.
2. Placing sidewalks along Elm St.

This Week:
1. Installation of 12” waterline under railroad structure.
2. Form and place reinforcing steel for rear and forward wingwalls for railroad structure phase 2.
3. Begin installing storm drainage thru structure to tie into 42” main storm sewer.
Next Week:
1. Complete forming and place concrete for rear and forward wingwalls for railroad structure phase 2.
2. Continue installing storm drainage thru structure.

This Week:
1. Installation of 12” waterline under railroad structure.
2. Form and place reinforcing steel for rear and forward wingwalls for railroad structure phase 2.
3. Begin installing storm drainage thru structure to tie into 42” main storm sewer.
Next Week:
1. Complete forming and place concrete for rear and forward wingwalls for railroad structure phase 2.
2. Continue installing storm drainage thru structure.

This Week:
1. Excavation thru bridge structure and retaining wall dismantling completed.
2. Form, place reinforcing steel, and pour concrete for rear and forward wingwall footers for railroad bridge.
3. Begin installing storm drainage thru bridge structure to tie into 42” main storm sewer.
Next Week:
1. Begin forming rear and forward wingwalls for railroad bridge.
2. Continue installing storm drainage thru bridge structure.

This Week:
1. Excavation thru bridge structure and retaining wall dismantling completed.
2. Form, place reinforcing steel, and pour concrete for rear and forward wingwall footers for railroad bridge.
3. Begin installing storm drainage thru bridge structure to tie into 42” main storm sewer.
Next Week:
1. Begin forming rear and forward wingwalls for railroad bridge.
2. Continue installing storm drainage thru bridge structure.

This Week:
1. Complete Bellefontaine Ave rail crossing.
2. Move train traffic to new mainline rail over new bridge.
3. Remove existing shoofly rail and ties.
Next Week:
1. Begin excavating material on the west side of the new rail.

This Week:
1. Complete Bellefontaine Ave rail crossing.
2. Move train traffic to new mainline rail over new bridge.
3. Remove existing shoofly rail and ties.
Next Week:
1. Begin excavating material on the west side of the new rail.

This Week:
1. Re-construct mainline railroad in preparation to returning track to the original alignment.
2. Erect detour for closing Bellefontaine Ave on Wednesday 9/03/19.
Next Week:
1. Close Bellefontaine Ave on Wednesday 9/03/19.
2. Install concrete railroad grade crossing on Bellefontaine Ave.
3. Continue re-constructing mainline railroad.
4. The weekend of 9/7 thru 9/8 return rail traffic to the original alignment.

This Week:
1. Re-construct mainline railroad in preparation to returning track to the original alignment.
2. Erect detour for closing Bellefontaine Ave on Wednesday 9/03/19.
Next Week:
1. Close Bellefontaine Ave on Wednesday 9/03/19.
2. Install concrete railroad grade crossing on Bellefontaine Ave.
3. Continue re-constructing mainline railroad.
4. The weekend of 9/7 thru 9/8 return rail traffic to the original alignment.

This Week:
1. Install steel plate expansion joints at each end of the bridge structure.
2. Remove bridge deck falsework from under structure.
3. Seed and mulch slopes along Elm St, Grove Ave, and Shawnee St.
Next Week:
1. Waterproof bridge deck.
2. Fine grade 304 stone ballast in preparation for rail re-construction scheduled to begin 8/19/19.

This Week:
1. Install steel plate expansion joints at each end of the bridge structure.
2. Remove bridge deck falsework from under structure.
3. Seed and mulch slopes along Elm St, Grove Ave, and Shawnee St.
Next Week:
1. Waterproof bridge deck.
2. Fine grade 304 stone ballast in preparation for rail re-construction scheduled to begin 8/19/19.

This Week:
1. Backfilling behind rear and forward abutments using 304 stone.
2. Preparing structure for deck concrete placement.
Next Week:
1. Placing deck concrete.
2. Completing backfill operations behind rear and forward abutments.
3. Begin excavating to subgrade for proposed railroad.
4. Begin placing topsoil along newly placed sidewalk

This Week:
1. Backfilling behind rear and forward abutments using 304 stone.
2. Preparing structure for deck concrete placement.
Next Week:
1. Placing deck concrete.
2. Completing backfill operations behind rear and forward abutments.
3. Begin excavating to subgrade for proposed railroad.
4. Begin placing topsoil along newly placed sidewalk

This Week:
1. Erecting structural steel for railroad bridge.
2. Placing concrete for left rear and forward wingwalls.
3. Fine grading 304 aggregate base in preparation for 301 asphalt base course on Elm St, Shawnee St, and Grove Ave.
4. Installation of light pole foundations and electric service to light poles on Elm St, Shawnee St, and Grove Ave.
5. Grading behind new curb in preparation for new sidewalks Elm St, Shawnee St, and Grove Ave.
Next Week:
1. Placing falsework for new concrete deck for the railroad bridge.
2. Begin backfilling behind rear and forward abutment and constructing wire faced mechanically stabilized earth wall.
3. Placing 301 asphalt base course and 448 Type 2 intermediate course on Elm St, Shawnee St, and Grove Ave
4. Grading behind new curb in preparation for new sidewalks Elm St, Shawnee St, and Grove Ave.

This Week:
1. Erecting structural steel for railroad bridge.
2. Placing concrete for left rear and forward wingwalls.
3. Fine grading 304 aggregate base in preparation for 301 asphalt base course on Elm St, Shawnee St, and Grove Ave.
4. Installation of light pole foundations and electric service to light poles on Elm St, Shawnee St, and Grove Ave.
5. Grading behind new curb in preparation for new sidewalks Elm St, Shawnee St, and Grove Ave.
Next Week:
1. Placing falsework for new concrete deck for the railroad bridge.
2. Begin backfilling behind rear and forward abutment and constructing wire faced mechanically stabilized earth wall.
3. Placing 301 asphalt base course and 448 Type 2 intermediate course on Elm St, Shawnee St, and Grove Ave
4. Grading behind new curb in preparation for new sidewalks Elm St, Shawnee St, and Grove Ave.

This Week:
1. Place concrete for forward abutment backwall seat for the railroad bridge.
2. Begin formwork rear and forward abutment wingwalls.
3. Complete excavation and underdrains for Shawnee St.
4. Place 304 aggregate base for Elm and Shawnee Streets.
5. Complete retaining wall #2 along Elm St adjacent to Memorial Hospital parking lot.
Next Week:
1. Place concrete for rear and forward abutment wingwalls for the railroad bridge.
2. Set curb grade for Elm and Shawnee Streets.
3. Bridge structural steel scheduled for 6/11/19.

This Week:
1. Place concrete for forward abutment backwall seat for the railroad bridge.
2. Begin formwork rear and forward abutment wingwalls.
3. Complete excavation and underdrains for Shawnee St.
4. Place 304 aggregate base for Elm and Shawnee Streets.
5. Complete retaining wall #2 along Elm St adjacent to Memorial Hospital parking lot.
Next Week:
1. Place concrete for rear and forward abutment wingwalls for the railroad bridge.
2. Set curb grade for Elm and Shawnee Streets.
3. Bridge structural steel scheduled for 6/11/19.

Last Week:
1. Complete forming the rear abutment wall and beam seat. Place 170 CY Class QC-4 Concrete for the railroad bridge.
This Week:
1. Begin forming for forward abutment wall and beam seat for the railroad bridge.
2. Excavate to subgrade along Elm and Shawnee east of railroad.
3. Install underdrains along Elm and Shawnee Streets.
4. Begin constructing retaining wall #2 along Elm St adjacent to the Memorial Hospital parking lot.

Last Week:
1. Complete forming the rear abutment wall and beam seat. Place 170 CY Class QC-4 Concrete for the railroad bridge.
This Week:
1. Begin forming for forward abutment wall and beam seat for the railroad bridge.
2. Excavate to subgrade along Elm and Shawnee east of railroad.
3. Install underdrains along Elm and Shawnee Streets.
4. Begin constructing retaining wall #2 along Elm St adjacent to the Memorial Hospital parking lot.

This Week:
1. Continue installation of storm drains along Elm St and Grove Ave east of the railroad.
2. Begin forming the rear abutment wall and beam seat for the railroad structure.
3. Begin placing underdrains along Elm and Grove Streets east of the railroad.
Next Week:
1. Continue installation of storm drains along Elm/Shawnee St.
2. Place reinforcing steel for the rear abutment wall and beam seat for the railroad structure.
3. Continue installing underdrains along Elm and Grove Streets east of the railroad.

This Week:
1. Continue installation of storm drains along Elm St and Grove Ave east of the railroad.
2. Begin forming the rear abutment wall and beam seat for the railroad structure.
3. Begin placing underdrains along Elm and Grove Streets east of the railroad.
Next Week:
1. Continue installation of storm drains along Elm/Shawnee St.
2. Place reinforcing steel for the rear abutment wall and beam seat for the railroad structure.
3. Continue installing underdrains along Elm and Grove Streets east of the railroad.

This Week:
1. Continue excavation operations along Elm/Shawnee St.
2. Continue installation of storm drains along Elm St and Grove Ave east of the railroad.
3. Place reinforcing steel and concrete for rear abutment footer for the railroad structure.
4. Form forward abutment footer for the railroad structure.
5. Begin installation of storm sewer on Elm/Shawnee St.
Next Week:
1. Continue installation of storm sewer along Elm/Shawnee St.
2. Place reinforcing steel and concrete for forward abutment footer for the railroad structure.
3. Begin forming rear abutment bridge seat and wall.
4. Excavate for temporary pavement along Bellefontaine Ave west of Elm St.

This Week:
1. Continue excavation operations along Elm/Shawnee St.
2. Continue installation of storm drains along Elm St and Grove Ave east of the railroad.
3. Place reinforcing steel and concrete for rear abutment footer for the railroad structure.
4. Form forward abutment footer for the railroad structure.
5. Begin installation of storm sewer on Elm/Shawnee St.
Next Week:
1. Continue installation of storm sewer along Elm/Shawnee St.
2. Place reinforcing steel and concrete for forward abutment footer for the railroad structure.
3. Begin forming rear abutment bridge seat and wall.
4. Excavate for temporary pavement along Bellefontaine Ave west of Elm St.

This Week:
1. Continue excavation operations along Elm St. east of the railroad.
2. Begin installation of storm sewer along Elm St. and Grove Ave. east of the railroad.
3. Excavate for the rear and forward abutment footings for the railroad bridge.
4. Form forward abutment footing and place reinforcing steel.
Next Week:
1. Continue installation of storm sewer along Elm St. and Grove Ave. west of the railroad.
2. Place concrete for forward abutment footing.
3. Form and place reinforcing steel for rear abutment footing.

This Week:
1. Continue excavation operations along Elm St. east of the railroad.
2. Begin installation of storm sewer along Elm St. and Grove Ave. east of the railroad.
3. Excavate for the rear and forward abutment footings for the railroad bridge.
4. Form forward abutment footing and place reinforcing steel.
Next Week:
1. Continue installation of storm sewer along Elm St. and Grove Ave. west of the railroad.
2. Place concrete for forward abutment footing.
3. Form and place reinforcing steel for rear abutment footing.

This Week:
1. Continuing excavation operations on Elm St and Grove Ave west of the railroad.
2. Installing the second row of tiebacks in the temporary retaining wall required to support the railroad during bridge construction.
Next Week:
1. Continue excavation operations along Elm St and Grove Ave west of the railroad.
2. Complete installation of the second row of tiebacks in the temporary retaining wall.
3. Excavate for the rear and forward abutment footings.
4. Begin installation of 8” water line along Grove Ave.

This Week:
1. Continuing excavation operations on Elm St and Grove Ave west of the railroad.
2. Installing the second row of tiebacks in the temporary retaining wall required to support the railroad during bridge construction.
Next Week:
1. Continue excavation operations along Elm St and Grove Ave west of the railroad.
2. Complete installation of the second row of tiebacks in the temporary retaining wall.
3. Excavate for the rear and forward abutment footings.
4. Begin installation of 8” water line along Grove Ave.

This Week:
1. Continued excavation operations on Elm St east of the railroad in preparation for the second row of tiebacks in the temporary retaining wall.
2. Continued oak lagging installation for the temporary retaining wall needed to support the railroad during construction of the new railroad bridge.
Next Week:
1. Continue excavation operations along Elm St west of the railroad.
2. Continue construction of the temporary retaining wall.
3. Begin installing the second row of tiebacks in the temporary retaining wall.

This Week:
1. Continued excavation operations on Elm St east of the railroad in preparation for the second row of tiebacks in the temporary retaining wall.
2. Continued oak lagging installation for the temporary retaining wall needed to support the railroad during construction of the new railroad bridge.
Next Week:
1. Continue excavation operations along Elm St west of the railroad.
2. Continue construction of the temporary retaining wall.
3. Begin installing the second row of tiebacks in the temporary retaining wall.

This Week:
1. Installation of the first row of tiebacks for the temporary retaining wall is complete. Tiebacks are required to provide stability for the wall.
2. Continued excavation operations on Elm St east of the railroad in preparation for the second row of tiebacks in the temporary retaining wall.
3. Continued construction of the temporary retaining wall needed to support the temporary railroad during construction of the new railroad bridge.
Next Week:
1. Continue excavation operations along Elm St east of the railroad.
2. Continue construction of the temporary retaining wall.
3. Begin installing the second row of tiebacks in the temporary retaining wall.

This Week:
1. Installation of the first row of tiebacks for the temporary retaining wall is complete. Tiebacks are required to provide stability for the wall.
2. Continued excavation operations on Elm St east of the railroad in preparation for the second row of tiebacks in the temporary retaining wall.
3. Continued construction of the temporary retaining wall needed to support the temporary railroad during construction of the new railroad bridge.
Next Week:
1. Continue excavation operations along Elm St east of the railroad.
2. Continue construction of the temporary retaining wall.
3. Begin installing the second row of tiebacks in the temporary retaining wall.

Last Week:
1. Continued excavation operations along Elm St. west of the railroad for the new Elm/Grove St intersection.
2. Continued construction of the temporary retaining wall needed to support the temporary railroad during construction of the new railroad bridge.
3. Continued installation of the first row of tiebacks for the temporary retaining wall. Tiebacks are required to provide stability for the wall.
This Week:
1. Continue excavation operations along Elm St west of the railroad.
2. Continue construction of the temporary retaining wall.
3. Century Link Local scheduled to complete the relocation of phone line at the Elm/Shawnee St intersection.

Last Week:
1. Continued excavation operations along Elm St. west of the railroad for the new Elm/Grove St intersection.
2. Continued construction of the temporary retaining wall needed to support the temporary railroad during construction of the new railroad bridge.
3. Continued installation of the first row of tiebacks for the temporary retaining wall. Tiebacks are required to provide stability for the wall.
This Week:
1. Continue excavation operations along Elm St west of the railroad.
2. Continue construction of the temporary retaining wall.
3. Century Link Local scheduled to complete the relocation of phone line at the Elm/Shawnee St intersection.

Last Week:
1. The CenturyLink National fiber line adjacent to the railroad has been relocated.
2. Resumed excavation operations for the proposed railroad structure over Elm St.
3. Resumed construction of the temporary retaining wall needed to support the shoofly during construction of the railroad bridge.
This Week:
1. Continue excavation operations along Elm St. east of the railroad.
2. Continue construction of the temporary retaining wall.
3. Continue installation of the first row of tiebacks for the temporary retaining wall.

Last Week:
1. The CenturyLink National fiber line adjacent to the railroad has been relocated.
2. Resumed excavation operations for the proposed railroad structure over Elm St.
3. Resumed construction of the temporary retaining wall needed to support the shoofly during construction of the railroad bridge.
This Week:
1. Continue excavation operations along Elm St. east of the railroad.
2. Continue construction of the temporary retaining wall.
3. Continue installation of the first row of tiebacks for the temporary retaining wall.

Last Week:
1. Completed the 20” water main installation along Shawnee and Elm Street.
2. Completed the 8” water line installation on Shawnee Street.
3. Began installing the 12” water line along Elm Street east of the proposed railroad bridge.
4. Placed topsoil and seeded along the new sidewalk in front of the Family of Faith Church.
This Week:
1. Perform required tests on new water lines on Elm and Shawnee Street in preparation of putting them in service.

Last Week:
1. Completed the 20” water main installation along Shawnee and Elm Street.
2. Completed the 8” water line installation on Shawnee Street.
3. Began installing the 12” water line along Elm Street east of the proposed railroad bridge.
4. Placed topsoil and seeded along the new sidewalk in front of the Family of Faith Church.
This Week:
1. Perform required tests on new water lines on Elm and Shawnee Street in preparation of putting them in service.

Last Week:
1. Continued the 20” water main installation along Shawnee and Elm Streets.
2. Completed replacing curb, sidewalk, and drive approaches at the Family of Faith Church parking lot removed during the 42” storm sewer installation.
3. Begin excavation for the proposed railroad structure ALL-ELM-0.81 behind the temporary retaining wall #1 in preparation for installing the first row of tiebacks.
This Week:
1. Complete the 20” water main installation along Shawnee and Elm Streets.
2. Continue excavation for the proposed railroad structure ALL-ELM-0.81 behind the temporary retaining wall #1 in preparation for installing the first row of tiebacks.
3. Install oak lagging planks between the H-pile for the proposed temporary retaining wall #1 required to support the embankment beneath the railroad during the construction of the bridge.

Last Week:
1. Continued the 20” water main installation along Shawnee and Elm Streets.
2. Completed replacing curb, sidewalk, and drive approaches at the Family of Faith Church parking lot removed during the 42” storm sewer installation.
3. Begin excavation for the proposed railroad structure ALL-ELM-0.81 behind the temporary retaining wall #1 in preparation for installing the first row of tiebacks.
This Week:
1. Complete the 20” water main installation along Shawnee and Elm Streets.
2. Continue excavation for the proposed railroad structure ALL-ELM-0.81 behind the temporary retaining wall #1 in preparation for installing the first row of tiebacks.
3. Install oak lagging planks between the H-pile for the proposed temporary retaining wall #1 required to support the embankment beneath the railroad during the construction of the bridge.

Last week:
1. Continue 36” storm sewer installation along the north side of
Bellefontaine Avenue.
2. Continue 20” waterline relocation along Shawnee Street.
3. Continue replacing curb, sidewalk, and the 42” storm sewer trenches in the bike path, the drive to Lima Senior Stadium, and the Family of Faith Church parking lot.
This week:
1. Complete 36” storm sewer installation along the north side of
Bellefontaine Avenue.
2. Continue 20” waterline relocation along Shawnee Street and Elm Street.
3. Continue replacing curb, sidewalk, and the 42” storm sewer trenches in the bike path, the drive to Lima Senior Stadium, and the Family of Faith Church parking lot.

Last week:
1. Continue 36” storm sewer installation along the north side of
Bellefontaine Avenue.
2. Continue 20” waterline relocation along Shawnee Street.
3. Continue replacing curb, sidewalk, and the 42” storm sewer trenches in the bike path, the drive to Lima Senior Stadium, and the Family of Faith Church parking lot.
This week:
1. Complete 36” storm sewer installation along the north side of
Bellefontaine Avenue.
2. Continue 20” waterline relocation along Shawnee Street and Elm Street.
3. Continue replacing curb, sidewalk, and the 42” storm sewer trenches in the bike path, the drive to Lima Senior Stadium, and the Family of Faith Church parking lot.

Last week:
1. Completed installation of the 42” storm sewer along the north side of Bellefontaine Avenue.
2. Began the installation of a 36” storm sewer along the north side of Bellefontaine Avenue.
3. Began replacing curb, sidewalk, and the 42” storm sewer trenches in the bike path, in the drive to Lima Senior Stadium, and in the Family of Faith Church parking lot.
This week:
1. Continue 36” storm sewer installation along the north side of
Bellefontaine Avenue.
2. Continue 20” waterline relocation along Shawnee Street.
3. Continue replacing curb, sidewalk, and the 42” storm sewer trenches in the bike path, in the drive to Lima Senior Stadium, and in the Family of Faith Church parking lot.

Last week:
1. Completed installation of the 42” storm sewer along the north side of Bellefontaine Avenue.
2. Began the installation of a 36” storm sewer along the north side of Bellefontaine Avenue.
3. Began replacing curb, sidewalk, and the 42” storm sewer trenches in the bike path, in the drive to Lima Senior Stadium, and in the Family of Faith Church parking lot.
This week:
1. Continue 36” storm sewer installation along the north side of
Bellefontaine Avenue.
2. Continue 20” waterline relocation along Shawnee Street.
3. Continue replacing curb, sidewalk, and the 42” storm sewer trenches in the bike path, in the drive to Lima Senior Stadium, and in the Family of Faith Church parking lot.

Last week:
1. Continue installation of the 42” storm sewer along the north side
of Bellefontaine Avenue (One westbound lane of Bellefontaine Avenue will be closed during storm sewer installation).
2. Shawnee Street closed Monday October 15th to begin replacing the existing 20” waterline along Shawnee St.
3. Begin replacing curb, sidewalk, and 42” storm sewer trenches in bike path, drive to Lima Senior Stadium, and Family of Faith Church parking lot.
This week:
1. Continue 42” storm sewer installation along the north side of
Bellefontaine Avenue.
2. Continue 20” waterline relocation along Shawnee Street.
3. Continue replacing curb, sidewalk, and 42” storm sewer trenches in bike path, drive to Lima Senior Stadium, and Family of Faith Church parking lot.

Last week:
1. Continue installation of the 42” storm sewer along the north side
of Bellefontaine Avenue (One westbound lane of Bellefontaine Avenue will be closed during storm sewer installation).
2. Shawnee Street closed Monday October 15th to begin replacing the existing 20” waterline along Shawnee St.
3. Begin replacing curb, sidewalk, and 42” storm sewer trenches in bike path, drive to Lima Senior Stadium, and Family of Faith Church parking lot.
This week:
1. Continue 42” storm sewer installation along the north side of
Bellefontaine Avenue.
2. Continue 20” waterline relocation along Shawnee Street.
3. Continue replacing curb, sidewalk, and 42” storm sewer trenches in bike path, drive to Lima Senior Stadium, and Family of Faith Church parking lot.

Shawnee Street will close Monday October 15th to begin replacing the existing 20” waterline in this area.

Shawnee Street will close Monday October 15th to begin replacing the existing 20” waterline in this area.

Last week:
1. Continued installation of a 42” storm sewer along the north side
of Bellefontaine Avenue. One westbound lane of Bellefontaine Avenue will be closed during storm sewer installation.
This week:
1. Continue 42” storm sewer installation along the north side of Bellefontaine Avenue.
2. Construct proposed headwall Sta 49+40 Lt Bellefontaine Avenue (42” Storm outlet into Ottawa River).

Last week:
1. Continued installation of a 42” storm sewer along the north side
of Bellefontaine Avenue. One westbound lane of Bellefontaine Avenue will be closed during storm sewer installation.
This week:
1. Continue 42” storm sewer installation along the north side of Bellefontaine Avenue.
2. Construct proposed headwall Sta 49+40 Lt Bellefontaine Avenue (42” Storm outlet into Ottawa River).

Last week:
1. Continued installation of a 42” storm sewer along the north side of Bellefontaine Avenue. One westbound lane of Bellefontaine Avenue will be closed during storm sewer installation.
This week:
1. Continue 42” storm sewer installation along the north side of Bellefontaine Avenue.
2. Shawnee Street will close Monday October 15th to begin replacing the existing 20” waterline in this area.

Last week:
1. Continued installation of a 42” storm sewer along the north side of Bellefontaine Avenue. One westbound lane of Bellefontaine Avenue will be closed during storm sewer installation.
This week:
1. Continue 42” storm sewer installation along the north side of Bellefontaine Avenue.
2. Shawnee Street will close Monday October 15th to begin replacing the existing 20” waterline in this area.

Last Week:
1. Completed construction of Retaining Wall #1 along the south side of Elm Street.
This Week:
1. Begin installation of a 42” storm drain along the north side of Bellefontaine Avenue. One westbound lane of Bellefontaine Avenue
will be closed during storm drain installation.
2. Shawnee St will close on Monday October 8th to begin replacing the existing 20” waterline in this area.

Last Week:
1. Completed construction of Retaining Wall #1 along the south side of Elm Street.
This Week:
1. Begin installation of a 42” storm drain along the north side of Bellefontaine Avenue. One westbound lane of Bellefontaine Avenue
will be closed during storm drain installation.
2. Shawnee St will close on Monday October 8th to begin replacing the existing 20” waterline in this area.

Last Week:
1. Continued construction of the proposed Retaining Wall #1 along the south side of Elm Street.
Next Week:
1. Continue construction of the proposed Retaining Wall #1 along the south side of Elm Street.
2. Begin installation of the proposed 42” storm sewer along Bellefontaine Ave. One lane of Bellefontaine Ave. will be
closed to westbound traffic during storm sewer installation.

Last Week:
1. Continued construction of the proposed Retaining Wall #1 along the south side of Elm Street.
Next Week:
1. Continue construction of the proposed Retaining Wall #1 along the south side of Elm Street.
2. Begin installation of the proposed 42” storm sewer along Bellefontaine Ave. One lane of Bellefontaine Ave. will be
closed to westbound traffic during storm sewer installation.

Last Week:
1. Completed construction of the temporary railroad (shoofly) connecting shoofly rail to the existing railroad.
2. Completed construction of the temporary railroad (shoofly) crossing at Bellefontaine Ave.
3. Continued construction of proposed retaining wall along Elm St. (Retaining Wall #1).
Next Week;
1. Continue construction of proposed retaining wall along Elm St. (Retaining Wall #1)

Last Week:
1. Completed construction of the temporary railroad (shoofly) connecting shoofly rail to the existing railroad.
2. Completed construction of the temporary railroad (shoofly) crossing at Bellefontaine Ave.
3. Continued construction of proposed retaining wall along Elm St. (Retaining Wall #1).
Next Week;
1. Continue construction of proposed retaining wall along Elm St. (Retaining Wall #1)

SR-117/SR-309 will close 7/24/18 at the Bellefontaine Ave railroad crossing for 7 days in order to construct the temporary railroad crossing at that location.

SR-117/SR-309 will close 7/24/18 at the Bellefontaine Ave railroad crossing for 7 days in order to construct the temporary railroad crossing at that location.

SR-117/SR-309 will close 7/24/18 at the Bellefontaine Ave railroad crossing for 7 days in order to construct the temporary railroad crossing at that location.

SR-117/SR-309 will close 7/24/18 at the Bellefontaine Ave railroad crossing for 7 days in order to construct the temporary railroad crossing at that location.



SR-117/SR-309 will close 7/24/18 at the Bellefontaine Ave railroad crossing for 7 days in order to construct the temporary railroad crossing at that location.
Last Week:
- Began constructing temporary railroad (Shoofly) around the proposed bridge location.
- Continued excavation operations along Elm St east of the railroad.
- Began installing oak lagging for the proposed retaining wall along Elm St.
- Relocated railroad crossing gate at the Bellefontaine Ave crossing.
Next Week:
- Continue constructing temporary railroad (Shoofly) around the proposed bridge location.
- Continue excavation operations along Elm St east of the railroad.
- Continue installing oak lagging for the proposed retaining wall along Elm St.
- SR-117/SR-309 will close 7/24/18 at the Bellefontaine Ave railroad crossing for 7 days in order to construct the temporary railroad crossing at that location.

Last Week:
- Began constructing temporary railroad (Shoofly) around the proposed bridge location.
- Continued excavation operations along Elm St east of the railroad.
- Began installing oak lagging for the proposed retaining wall along Elm St.
- Relocated railroad crossing gate at the Bellefontaine Ave crossing.
Next Week:
- Continue constructing temporary railroad (Shoofly) around the proposed bridge location.
- Continue excavation operations along Elm St east of the railroad.
- Continue installing oak lagging for the proposed retaining wall along Elm St.
- SR-117/SR-309 will close 7/24/18 at the Bellefontaine Ave railroad crossing for 7 days in order to construct the temporary railroad crossing at that location.

Last Week:
- Completed drilling shafts for soldier pile retaining wall along the south side of Elm St.
- Began excavation operations east of railroad in preparation for constructing retaining wall.
- Continued excavation for shoofly and placing sub ballast.
- Installed miscellaneous erosion control items.
This week:
- Begin shoofly rail construction. Installing ballast and railroad ties.
- Relocate railroad crossing gate and signal at the Bellefontaine Ave crossing.
- Continue excavation operations east of railroad in preparation for constructing retaining wall.
- Remove existing light poles along the left side of Bellefontaine Ave.

Last Week:
- Completed drilling shafts for soldier pile retaining wall along the south side of Elm St.
- Began excavation operations east of railroad in preparation for constructing retaining wall.
- Continued excavation for shoofly and placing sub ballast.
- Installed miscellaneous erosion control items.
This week:
- Begin shoofly rail construction. Installing ballast and railroad ties.
- Relocate railroad crossing gate and signal at the Bellefontaine Ave crossing.
- Continue excavation operations east of railroad in preparation for constructing retaining wall.
- Remove existing light poles along the left side of Bellefontaine Ave.

Last week:
- Continued drilling shafts and installing soldier piles for the temporary wall supporting the shoofly.
- Began excavation for Elm St. beginning at Stadium Drive to Grove Street.
- Continued excavation for shoofly.
- Completed house removal. All debris was removed from project.
- Seeding and Mulching on Park Access Drive.
This week:
- Completed installing soldier piles for temporary wall.
- Began drilling shafts and installing soldier piles for Retaining Wall #1.
- Continued excavating for shoofly.
- Place 304 stone and sub ballast for shoofly.

Last week:
- Continued drilling shafts and installing soldier piles for the temporary wall supporting the shoofly.
- Began excavation for Elm St. beginning at Stadium Drive to Grove Street.
- Continued excavation for shoofly.
- Completed house removal. All debris was removed from project.
- Seeding and Mulching on Park Access Drive.
This week:
- Completed installing soldier piles for temporary wall.
- Began drilling shafts and installing soldier piles for Retaining Wall #1.
- Continued excavating for shoofly.
- Place 304 stone and sub ballast for shoofly.

Please see the current schedule overview for the project.

Please see the current schedule overview for the project.

The Project kicked-off today with the groundbreaking ceremony! A special thanks to all who attended!

The Project kicked-off today with the groundbreaking ceremony! A special thanks to all who attended!

The City’s contractor will be closing E. Elm Street between Grove Avenue and Shawnee Street on May 2nd and will remain closed for the duration of the project.

The City’s contractor will be closing E. Elm Street between Grove Avenue and Shawnee Street on May 2nd and will remain closed for the duration of the project.

The City of Lima’s contractor, Eagle Bridge, began construction on April 30th. Expected completion: November 2019

